Power company says "fuck you" to people to serve AI..

"Lake Tahoe’s main energy source is being diverted to power #AI data centers"

"Nevada-based #NVEnergy will stop providing 75 percent of Liberty Utilities’ electricity for the #California side of Lake Tahoe by May 2027, affecting about 49,000 customers to meet growing demand from AI-driven data centers in #Nevada, Fortune reports."

independent.co.uk/news/world/a…

in reply to stux⚡️

"meet growing demand"

"mmuhhhaahhaaaarrrggh u silly smol users, look at us selling ur precious Watts wholesale in GigaWatts!"

in reply to stux⚡️

Meanwhile on the other side of the country in Virginia, those who consume 25MW or more and have a load factor (average usage/peak usage) of at least 75% have to sign a 14 year contract and have a significant minimum charge which is due through the end of the contract, even if they shut down earlier: datacenterdynamics.com/en/news…